MULTAN, (Pakistan Point News - APP - 15th August, 2016) : The work on Metro Bus project has entered the final phase as carpetting at Metro flyovers has been completed here. The work on carriage-way has already been finished, said an official handout, issued here on Monday. It informed that work on renovation of 21 Metro Stations was being completed at a fast pace. Similarly, 80 per cent of footpath from Bahauddin Zakariya University to Afshaar Chowk has been completed. Drivers of Metro Bus Service would start test-driving after widening of Kumharan Chowk, which was in progress, said the release.